12-19-2022 |
Decision |
|
|
|
on land we manually adjusted sites to fit. John originally wanted anything over 650 to be adjusted to 650 and anything between 650 and 450 to 450 |
|
|
12-19-2022 |
Decision |
|
|
|
John adjusted his region down 15% for sweeps over 180, some sweeps that were at 150 were adjusted down 15% as well |
|
|
12-13-2022 |
Pricing Strategy |
LandLot |
|
|
Bruce and Scott have agreed to adjust margin by 5% on sites where we are yellow, and 10% on sites where we are red to have a better chance to retain business |
|
|
12-13-2022 |
Pricing Strategy |
Land |
12-13-2022 |
|
Jason and Scott agreed on changes to margin of 5% for sites where we received feedback as yellow, and 8% on sites where we have received feedback where we are red |
|
|
11-23-2022 |
Decision |
|
|
|
Typical submittal margin is around 18%.
RAM sites- higher margin because we struggle to find sweepers- 33%
Leave incumbent at 24% move non incumbent up to 28%
Cap increase in price to 50% from stores that were losing or below margin |
|
|
11-21-2022 |
Meeting |
|
|
|
Dan Shafer
- CA no start up or shut down for irrigation
- WA $150-225 for start- up and shut down
- Monitoring: $125 across the board
- non mow visits- 2 hours (pends on sq footage of the site)
- Check with Mark Grant on Tru green program from Kroger regarding pest control- Dan
- Per visit minimum - $80
- Match any incumbent pricing across all 3 states
LOT SWEEP
- Minimum of $60 provider cost/ sweep
- Porter rate $42 |
|
|
11-21-2022 |
SOW |
|
|
|
Landscape:
- Inspection/ observation
- Turf management
- Tuf Ferts
- Weed control
- Pest Control (Tier 1)
- Mulch application (2")
- Dead or missing plant materials
- Tree and shrub pruning (includes palms)
- Tree and shrub fertilization
- Spring Clean- UP (Tier 1 and 2)
- Irrigation mgmt (weather trak/ hydropoint)
|
|
|
11-21-2022 |
Meeting |
|
|
|
Ashley T.
- 8 down to 6 prunes for LA, TX
- Turf ferts 4 to 3 in TX
- minimum's $75 across the board to get on site
- No start-up or shut down unless there is a freeze
- Monitoring for TX, flat rate $100-$115 across the board
- NEED AERIATION PRICING
- Spring and fall clean ups cut in half to 5- typically do not do them in TX
- Ashley going to sky spec 2 sites in Mt pleasant and Ft worth to confirm pricing- thinking pest control could be driving up the price for Tier 1 sites- brought down to 35 cents and cut price in half
LOT SWEEP
- $85-$90 per sweep is minimum (current incumbent pricing is too low)
- Porter rate $35 at 3X per week is confirmed |
|
|
11-21-2022 |
Decision |
|
|
|
Bruce sites:
- 6 to 2 ferts,
- 6 to 2 prunes (spring and fall)
- $110 start up/ $150 shut down/ $110 monitoring (flat rate)
|
|
|
11-21-2022 |
Decision |
|
|
|
Keep fire ant cost very minimal- should be part of pest control. (Bruce and Scott) Expect turf provider to take care of this. |
|
|
11-21-2022 |
Action |
|
|
|
Bruce can get seasonal cost for pest control |
|
|
11-21-2022 |
Risk |
|
|
|
concerns on how we price a removal of over 36' |
|
|
11-21-2022 |
General Note |
|
|
|
Bruce's team removed all the fertilization in pricing for Mid year because they believe they can get away with two and want to look lower on pricing
Aeration/overseeding is being priced by True Green
|
|
|
11-09-2022 |
Meeting |
|
|
|
Key dates and deadlines
- Submit by 11:59PM 11/27
- Get submitted by Wednesday 11/23 (before Thanksgiving)
? Potentially look at getting coaching?
- Commencement of work 2/1/23
? Scott thinks it will push to March due to lack of time
- How many rounds? Probably one because of lack of time
Questions due by Thursday 11/10 |
|
|
11-09-2022 |
General Note |
|
|
|
Strategy
- Need more clarification on what states we want to go after the most
- How will client award the business?
? Awarding site by site
- Putting extra emphasis on going in and checking in with stores during inspections
- Complete inspection every 30 days and add to last wo of the month
We already do this anyways |
|
|
11-09-2022 |
SOW |
|
|
|
SOW discussion and highlights
- Scott sending out brief overview of SOW
? Every store required to have a monthly wet check- very clear in SOW
- Description on mid-season clean up- send to Jason and group
? In SOW
- Aeriation and overseeding on fall clean up doesn’t make sense and will price us out of the bid.
? Tier 1 sites only for aeriation/ overseeding 123/1800 stores
- No column for remediation, where can we include in the bid? Spring clean- up?
- Mulch under cubic feet should be cubic yards
Check site In GA |
|
|
11-09-2022 |
Action |
|
|
|
ACTION items:
- Field to have specs verified by Friday
- Pull into pricing model next week/ early next week
- Set up time with field end of next week
? m,t , w strategize with Lowe's team
- Scott send incumbent numbers
- Pull in prior to bids or comparison accounts
? Compare apples to apples and not season total
Clint set up meetings with field next Friday |
|
|
09-22-2022 |
Meeting |
|
|
|
Met with Scott and Vince- discussed ongoing expectations on when an RFP will drop. Lowe's is forgoing the second year of DMG contract. |
|
|
09-22-2022 |
General Note |
|
|
|
scott anticipating RFP drop in the next 30 days. Still hasn't received confirmation from contact. |
|
|
09-22-2022 |
General Note |
|
|
|
Original contract is all inclusive, now they want to separate everything out- Scott |
|
|
09-22-2022 |
Key Assumption |
|
|
|
Separating work out because a lot of providers are not going out and doing the work. There will be separate WO's for each trade. |
|
|
09-22-2022 |
Risk |
|
|
|
Mulch was a big issue because RAMs or DM's didnt spec the property correctly- RAM areas scare Scott the most if we bid those locations. We are only there every 90 days.
|
|
|
09-22-2022 |
Action |
|
|
|
PI team re spec these sites to make sure they are correct, then have field team verify. |
|
|
09-22-2022 |
Risk |
|
|
|
pay for performance and admin fees for missed work or unsatisfactory work -$250 on future work orders if the incomplete work isn't closed out |
|